a. Using the schedule developed during Chapter 5 (see attached), estimate the cost for each activity.If using Microsoft Project, enter the rates of the work and material resources on the Resource Sheet. Assign the cost resource amount on the Task Information window for the task where the resource is assigned. Any resources that are not assigned to work the duration of a work package should have a percent of effort assigned, or the task should be changed to a fixed duration and the amount of work changed.b. Determine the TBC for the project using the top-down or the bottom-up approachIf using Microsoft Project and assigning the costs to the work packages, the approach is bottom-up.·a) top-down = allocates a portion of the total project cost to each work package.·b) bottom-up = sums the costs of all the activities that make up that work package.
the_wedding_case_study_shinton.docx

Unformatted Attachment Preview

Shayla Hinton 0595188
MGMT 4335 25734
The Wedding
10/14/16
Chapter 4
a. Work Breakdown structure
1. Wedding Management
1.1 Create teams
1.2 Set team tasks
1.3 Determine Wedding locations
2. Resources Management
2.1Wedding Funding
2.2 Shopping
2.2.1 Wedding rings
2.2.2 Wedding dresses
2.2 Create Wedding Budget
2.2.1 Venue reservation
2.2.2 Church reservation
2.2.3 Vehicle hiring
2.2.4 Venue decoration
2.2.5 Food and drinks
3. Task Management
3.1 Venue supervision
3.2 Food and drinks preparation
3.3 Photo shooting
End
b. List of Activities
The following activities will be done between now and the wedding day.
Shayla Hinton 0595188
MGMT 4335 25734
The Wedding
10/14/16
i.
ii.
iii.
iv.
v.
vi.
vii.
viii.
ix.
Establishing the wedding location
Creating the budget
Planning on dresses
Selecting wedding venue
Creating a wedding guest list
Selecting the wedding party groomsman and bridesmaids
Dancing/singing preparation
Planning on entertainment
Funding the wedding
c. Person responsible for each activity
Each activities will be supervised and accomplished by specific people as follows:
i.
ii.
iii.
iv.
v.
vi.
vii.
viii.
ix.
Establishing the wedding location
– Tony
Creating the budget
– Tony
Planning on dresses
– Peggy
Selecting wedding venue
– Peggy
Creating a wedding guest list
– Tony
Selecting the wedding party groomsman and bridesmaids – Tony
Dancing/singing preparation
– Peggy
Planning on entertainment
– Peggy
Funding the wedding
– Tony’s parents
d. Network diagram
The activities are marked as i – x as numbered in section c above. The network diagram is as
follows:
Chapter 5
a. Estimated Activity Duration
Shayla Hinton 0595188
MGMT 4335 25734
The Wedding
10/14/16
#
Activity
Estimated
duration
i
ii
iii
iv
v
vi
vii
viii
Establishing the wedding location
Creating the budget
Planning on dresses
Selecting wedding venue
Creating a wedding guest list
Selecting the wedding party groomsman and bridesmaids
Dancing/singing preparation
Planning on entertainment
Funding the wedding
12
24
18
12
6
12
24
36
36
b. ES, EF, LS, and LF times and total slack
Activity duration (days)
ES
EF
LS
LF
Total
slack
i
12
0
12
12
12
0
ii
24
0
24
24
36
12
iii
18
12
30
30
48
18
iv
12
12
24
24
24
0
v
36
30
66
66
84
18
vi
60
24
84
84
84
0
vii
24
24
48
48
60
12
viii
30
48
78
84
84
6
ix
36
84
120
120
120
0
c. The critical path is i-iv-vi-ix. The activities are Establishing the wedding location,
Selecting wedding venue, electing the wedding party groomsman and bridesmaids and then
Funding the wedding
d. Gantt chart